Whitmore Proposed Projects
PROJECT | ESTIMATE |
---|---|
Add electronic HVAC controls | $190,000 |
Domestic water line replacement | $650,000 |
Sewer line replacement | $385,000 |
Lighting - Exterior Dusk/Dawn Parking Lot | $25,000 |
Master Meters - Natural Gas | $20,000 |
Flooring replacement | $387,000 |
Building Renovations | $225,000 |
2 sunshades for courts | $200,000 |
4 LED lights, 2 per court | $4,800 |
2 portable bleachers | $4,600 |
Furniture/Equipment | $75,000 |
TOTAL | $2,166,400 |
See Building Renovations under Repairs
PROJECT | ESTIMATE |
---|---|
Security Gates / Fencing | $185,000 |
Security camera system | $70,000 |
New Intercom system | $80,000.00 |
Security window film | $110,000 |
Interior Emergency Lighting | $15,000 |
TOTAL | $460,000 |
PROJECT | ESTIMATE |
---|---|
Panels and Other Classroom Tech |
$40,230 |
Chromebooks & iPads |
$308,511 |
TOTAL | $348,741 |
* The projected costs provided here are estimates based on information available as of June 2023. Final estimates are determined when each project is designed for the specific site and the district enters into a contract. Actual costs are determined at the completion of work.