PROJECT | ESTIMATE |
---|---|
Replace all package AC units | $250,000 |
Domestic water line replacement | $650,000 |
Sewer line replacement | $385,000 |
Lighting - Exterior Dusk/Dawn Parking Lot | $25,000 |
Flooring replacement | $387,000 |
Building Renovations | $225,000 |
2 sunshades for courts | $200,000 |
4 LED lights, 2 per court | $4,800 |
2 portable bleachers | $4,600 |
Pavement preservation | $150,000 |
Furniture/Equipment | $75,000 |
TOTAL | $2,356,400 |
See Building Renovations under Repairs
PROJECT | ESTIMATE |
---|---|
Security Gates / Fencing | $185,000 |
Security camera system | $70,000 |
New Access Control devices | $20,000 |
Interior Emergency Lighting | $15,000 |
TOTAL | $295,000 |
PROJECT | ESTIMATE |
---|---|
Panels and Other Classroom Tech |
$40,230 |
Chromebooks & iPads |
$308,511 |
TOTAL | $348,741 |