Steele Proposed Projects
PROJECT | ESTIMATE |
---|---|
Lighting - Exterior Dusk/Dawn Parking Lot | $25,000 |
Domestic water line replacement | $650,000 |
Sewer Line Replacement | $365,000 |
Flooring replacement | $87,500 |
Building Renovations | $225,000 |
2 sunshades for courts | $200,000 |
4 LED lights, 2 per court | $4,800 |
2 portable bleachers | $4,600 |
Pavement preservation | $140,000 |
Furniture/Equipment | $75,000 |
TOTAL | $1,796,900 |
See Building Renovations under Repairs
PROJECT | ESTIMATE |
---|---|
Security Gates / Fencing | $185,000 |
Security camera system | $70,000 |
New Access Control devices | $25,000 |
Interior Emergency Lighting | $15,000 |
TOTAL | $295,000 |
PROJECT | ESTIMATE |
---|---|
Panels and Other Classroom Tech |
$40,230 |
Chromebooks & iPads |
$308,511 |
TOTAL | $348,741 |
* The costs provided here are estimates based on information available as of June 2023. Actual costs will be determined when each project is designed for the specific site and the district enters into a contract.