Manzo Proposed Projects
PROJECT | ESTIMATE |
---|---|
Replace all package AC units | $250,000 |
Add electronic HVAC controls | $210,000 |
Domestic water line replacement | $650,000 |
Master Meters - Natural Gas | $20,000 |
Lighting - Exterior Dusk/Dawn Parking Lot | $25,000 |
Sewer line replacement | $385,000 |
Replace Single-pane Windows | $51,000 |
Flooring replacement | $387,000 |
Building Renovations | $225,000 |
4 LED lights, 2 per court | $4,800 |
2 sunshades for courts | $200,000 |
2 portable bleachers | $4,600 |
Furniture/Equipment | $75,000 |
TOTAL | $2,487,400 |
PROJECT | ESTIMATE |
---|---|
Demo Portables and add a quad building |
$1,000,000 |
TOTAL | $1,000,000 |
PROJECT | ESTIMATE |
---|---|
Security Gates / Fencing | $185,000 |
Security window film | $120,000 |
Interior Emergency Lighting | $15,000 |
TOTAL | $320,000 |
PROJECT | ESTIMATE |
---|---|
Panels and Other Classroom Tech |
$40,230 |
Chromebooks & iPads |
$308,511 |
TOTAL | $348,741 |
* The projected costs provided here are estimates based on information available as of June 2023. Final estimates are determined when each project is designed for the specific site and the district enters into a contract. Actual costs are determined at the completion of work.