Kellond Proposed Projects

Kellond Logo
PROJECT ESTIMATE

Convert obsolete HVAC controls

$230,000

Lighting - Exterior Dusk/Dawn Parking Lot

$25,000

Sewer line replacement

$385,000

Master Meters - Natural Gas

$20,000

Domestic water line replacement

$650,000

Building Renovations

$225,000

Flooring replacement

$387,000

2 sunshades for courts

$200,000

2 portable bleachers

$4,600

4 LED lights, 2 per court

$4,800

Marquee

$62,500

Pavement preservation

$140,000

Furniture/Equipment

$75,000

TOTAL $2,408,900
See Building Renovations under Repairs
PROJECT ESTIMATE

Security Gates / Fencing

$185,000

Security camera system

$70,000

New Access Control devices

$25,000

New Intercom system

$75,000

Interior Emergency Lighting

$15,000

TOTAL $370,000
PROJECT ESTIMATE

Panels and Other Classroom Tech

$40,230

Chromebooks & iPads

$308,511

TOTAL $348,741
Kellond School Building
* The costs provided here are estimates based on information available as of June 2023. Actual costs will be determined when each project is designed for the specific site and the district enters into a contract.